电抗器在南水北调台儿庄泵站 110 kV 输电线路中的应用

  • 打印
  • 收藏
收藏成功

DOI:10.19981/j.CN23-1581/G3.2026.12.045

中图分类号: TM714.3

文献标志码:A

文章编号:2095-2945(2026)12-0181-04

Abstract: This paper describes in detail the basic principle of the reactor, including the obstruction of inductance on current changes. Different types of reactors, such as air-core reactors, iron-core reactors, etc., are introduced, and their respective characteristics are analyzed. This paper discusses various applications of reactors in power systems, such as limiting short circuit current, reactive power compensation, etc., and also mentions the key points of reactor design and selection, operation maintenance and future development trends.

Keywords: South-to-North Water Diversion Project; pump station; reactor; impedance; reactive power compensation

台儿庄泵站工程是南水北调东线一期工程的第七级泵站,位于山东省枣庄市台儿庄区境内,为I等工程,设计调水流量 125m3/s ,站内安装5台全调节立式轴流泵(其中1台备用),单机设计流量 31.25m3/s ,配套电机功率为 2400kW ,总装机容量 12000kW 。(剩余5782字)

目录
monitor