既有建筑改造EPC项目成本超支影响因素研究

  • 打印
  • 收藏
收藏成功


打开文本图片集

Research on the Influencing Factors of Cost Overrun in EPC Projects for Renovation of Existing Buildings

SUN Mingyang1,²

(1.Shenzhen Futian Investment Holding Co.,Ltd., Shenzhen 5180oO,China; 2.School of Management Science and Real Estate,Chongqing University,Chongqing 4Oo045,China)

Abstract:Identifying the keyinfluencing factors ofcost overun isof greatsignificance forthecost control of EPC projects for existing building renovation.Theexpert interview method wasadopted to initially identify22 influencing factors of cost overrun in such EPC projects;the DEMATEL-ISM model was constructed to analyze the relationships among these 22 factors and identify four key influencing factors:completion status of the preliminary design,the lumpsum contract mode,the clarityof the design specification stipulated inthe bidding documents,and theclarity of the pricingbasis.This study provides reasonable suggestions forthe managementof cost overrun inEPC projects for existing building renovation.

Keywords: renovation of existing buildings; EPC projects ; cost overrun; influencing factors

0 引言

我国新型城镇化进程已经进入以“存量提质”为主导的发展新阶段,既有建筑改造和更新项目作为新型城镇化“提质”的核心路径,成为城市更新从“规模扩张”向“质量提升”转型的必然选择。(剩余7329字)