富水砂卵石地层基坑降水工程的设计与施工


打开文本图片集

【摘  要】深基坑降水是确保工程安全的重要工程技术措施。论文以成都地铁4号线二期南熏大道站基坑降水工程为例,论述了基坑降水方案设计方法,得到了基坑涌水量及降水井数量。通过南熏大道站基坑降水工程实践,效果显著,可为成都地区富水砂卵石地层类似工程基坑降水提供技术参考。

【Abstract】Deep foundation pit dewatering is an important technical measure to ensure engineering safety. Taking the foundation pit dewatering project of Nanxun Dadao station in the second phase of Chengdu Metro Line 4 as an example, this paper discusses the design method of foundation pit dewatering scheme, and obtains the water inflow of foundation pit and the number of dewatering wells. Through the practice of foundation pit dewatering in Nanxun Dadao station, the effect is remarkable, which can provide technical reference for similar projects of foundation pit dewatering in water-rich sandy pebble stratum in Chengdu area.

【關键词】富水砂卵石地层;基坑降水;设计;施工

【Keywords】water-rich sandy pebble stratum; foundation pit dewatering; design; construction

【中图分类号】U231+.3                                             【文献标志码】A                                                 【文章编号】1673-1069(2021)12-0188-03

1 工程概况

成都地铁4号线二期工程西延线主要位于成都市温江区与青羊区,线路全长10.923km,起于温江大学城站,出站后沿海科路、南熏大道和光华大道,由西向东敷设至一期工程起点(公平站)。(剩余5234字)